New Page 1
Introduction
The 51st
Meeting of the Executive Committee, which took place in Montreal from 19 to 23
March 2007, was attended by the representatives of the 14 Executive Committee
member Parties and by participants co-opted from 21 other countries (see
attached list). Mr. Philippe Chemouny of Canada presided over his first
meeting as Chair of the Executive Committee. The President and Vice-President
of the Implementation Committee of the Montreal Protocol, three representatives
of the Ozone Secretariat, representatives of the implementing agencies and
representatives of the Alliance for Responsible Atmospheric Policy and
Environmental Investigation Agency (EIA) also attended the meeting.
The
Executive Committee followed its standard programme of work for the first
meeting of the year which included the consideration of business plans,
evaluation reports and the implementing agencies’ work programmes. Business
planning, the process of allocating financial resources to Article 5 countries
according to their compliance needs, was especially important since the 2010
targets for CFC phase-out were only three years away. A number of other issues
were addressed including the progress and finalisation of contracting a
consultant for the study on the treatment of unwanted ozone depleting substances
(ODS) and the terms of reference for a study on administrative costs of
implementing agencies beyond 2008.
At the
51st Meeting, the Executive Committee approved investment projects and work
programme activities with a value of almost US $50.7 million, plus US $3.9
million in support costs for implementing agencies, and took a total of 39
decisions. The most significant decisions and discussions are outlined below.
Status of
contributions and disbursements (decision 51/2)
The
Executive Committee reviewed information on the Fund’s balance, income and
contributions, and aggregate information on the status for the triennium,
including data on gains and losses of the fixed-exchange rate mechanism (FERM)
and addressed issues relating to the timely payment of contributions by Parties
and the liquidity of resources. In addition to the standard information in the
report on the status of contributions, the Executive Committee also considered
the encashment schedule for the existing promissory notes, a new feature of the
report of the Treasurer that had been included in response to concerns about the
rate of encashment of promissory notes.
The
Executive Committee was concerned that only 9.87% of the total amount of
contributions pledged for 2007 had been paid by the time of the 51st Meeting and
therefore urged contributing Parties to pay their contributions to the
Multilateral Fund in full as early as possible. At the time of the 51st
Meeting, the Fund balance stood at US $57,516,295, which was adequate to cover
the new commitments entered by the Executive Committee at the meeting.
Review of
Promissory notes policy (decision 51/3)
The
Executive Committee reviewed the Multilateral Fund’s policies regarding the use
of promissory notes in making contributions, and requested Parties continuing to
use promissory notes to do their utmost to meet the Treasurer’s request for
their accelerated encashment in order to mitigate cash flow problems. The
Committee also encouraged Parties, in the context of the 2009-2011
replenishment, to make their contributions in the form of cash in order not to
delay project implementation by implementing agencies.
2007-2009
Business Plans (decisions 51/5 - 51/10)
The
Executive Committee endorsed the 2007-2009 business plans for its four
multilateral agencies (UNDP, UNEP, UNIDO and the World Bank) and a number of
bilateral agencies to address the compliance needs for achieving the 2010
control measures. The Committee urged bilateral and implementing agencies to
increase their efforts to implement approved projects to facilitate achieving
the 2007 reduction in controlled substances. 35,945 ODP tonnes of these
substances were scheduled to be phased out in 2007 from approved projects.
The
Executive Committee also established a number of specific priorities to allocate
the US $61 million in addition to the activities which were required by the
three year phase-out plan for compliance. These priorities would include support
to any new Parties to the Montreal Protocol including strengthening of
institutional capacity to implement the Protocol’s control measures, on a case
by case basis. Another priority would be accelerating the elimination of CFC
production, and in this regard the World Bank was requested to investigate the
possibilities of advanced CFC and CTC production closure and to report back to
the Executive Committee on any issues it encountered.
Other
priorities that would be considered on a case by case basis included combating
illegal trade in ODS, halon phase-out not required by the model three year
rolling phase-out plan, accelerated methyl bromide (MB) phase-out, MB
non-investment projects, and phase-out of CFCs in metered-dose inhalers.
Programme
Implementation
Monitoring and Evaluation
Final report on the evaluation of CTC phase-out projects and agreements
(decision 51/11)
The
Executive Committee considered the final report on the evaluation of CTC
phase-out projects and agreements, which showed that all but eight Article 5
countries had met the 2005 target to reduce CTC consumption by 85 per cent.
The evaluation study found that the main risk to sustaining phase-out lay in the
fact that, unlike other controlled substances produced for specific uses, CTC
was also generated as a by-product and therefore would be available even after
phasing-out CTC production for controlled uses. The successful achievement of
the Protocol’s control measures would therefore depend on controlling and
eventually eliminating the demand for CTC in controlled uses, as well as further
development of outlets for feedstock uses in manufacturing non-ODS products. Any
opportunities to sell co-produced CTC for process agent or solvent uses might
bring higher returns than CTC destruction, with an ensuing risk of CTC being
placed on the market without licenses. CTC at a low price could result in a risk
of illegal use, and thus ongoing monitoring systems would be vital.
In
addition to addressing some particular issues related to CTC production and
consumption in China and India, the Executive Committee requested implementing
agencies to update their information materials on alternatives to CTC especially
in the solvent sector, avoiding as much as possible the use of trade names and
of potentially carcinogenic solvents. UNEP was requested to organize discussions
in regional network meetings about the possibility of voluntary agreements
between CTC exporting and importing countries under which CTC exporting
enterprises, prior to shipment, would have to request certificates from their
importing clients to verify imports for feedstock use or under a valid import
license obtained through the importing country's quota system. The Executive
Committee also decided to take into account, in future deliberations on the
funding of institutional strengthening projects, the need to maintain monitoring
and verification of all CTC production and consumption beyond 2010. The final
report on the evaluation of CTC phase-out projects and agreements would be
forwarded to the Technology and Economic Assessment Panel (TEAP) so that it
could be taken into account in their further discussions on process agents.
Desk study on the evaluation of management and monitoring of national phase-out
plans (decision 51/12)
The
Executive Committee noted the desk study on the evaluation of management and
monitoring of national ODS phase-out plans, which contained information on the
proposed evaluation issues and work plan for the second phase of the evaluation
study. The objective of the study was to complement the evaluation of
refrigerant management plans and national phase-out plans in non low-volume
consuming countries presented at the 48th Meeting of the Executive Committee.
That study focused primarily on the refrigeration sector and was not able to
analyze in depth the management, monitoring and verification aspects of national
phase-out plans.
One policy
issue addressed was the flexibility clause as it applied to the disbursement of
funds under national phase-out plans to enterprises established after the
cut-off date of July 1995. Flexibility in the use of funds has been a key
provision of national phase-out plans in Article 5 countries (decision 38/65).
Decision 46/37 elaborates the conditions applicable to agreements for the
exercising of such flexibility in the use of funds by defining major and minor
changes to endorsed annual implementation plans. The Executive Committee
requested that implementing agencies seek authorization from the Executive
Committee prior to using this flexibility to allow funds to be directed to
enterprises established after July 1995 in cases where countries had committed
to the total phase-out of the ODS concerned. It also requested bilateral and
implementing agencies to report as part of their regular periodic reporting
under multi-year-agreements whether they had used the flexibility clause for
this purpose.
Issues related to monitoring and reporting on multi-year agreements (decision
51/13)
The
Executive Committee agreed on new procedures for monitoring and tracking
difficulties in the implementation of multi-year agreements (MYAs). Project
proposals presented to the Executive Committee (pre-session documents) would
contain a cover-sheet in an interim format that would present a standard
overview of data on MYAs and allow the Committee to track cumulative progress
achieved in the annual work programmes. The Executive Committee also approved
new procedures for monitoring implementation difficulties in MYAs which were
defined as activities for which no progress was detected in the context of the
review of annual implementation plans. Any status reports on MYAs with
implementation difficulties required by the Executive Committee would be
presented in the format of projects with implementation delays and would be
considered by the Executive Committee in the context of that agenda item.
Project implementation delays (decision 51/14)
Of the 66
projects listed with implementation delays at the 51st Meeting, the Executive
Committee noted that 19 had been completed. Letters of possible cancellation
would be sent to two countries concerning project implementation delays. The
Executive Committee also made specific requests to a number of Governments
suggesting ways to move projects forward in order to effect the timely
implementation of these projects.
Annual tranche submission delays (decision 51/15)
The
Executive Committee reviewed all annual tranches of MYAs due for submission to
the 51st Meeting noting that 16 of the 38 annual tranches had not been submitted
on time. Letters regarding tranches not submitted to the 51st Meeting would be
sent to eleven countries encouraging them to submit these to the 52nd Meeting.
Report on
implementation of approved projects with specific reporting requirements
(decision 51/16)
At its
51st Meeting the Executive Committee considered progress reports on the
implementation of: the national CFC phase-out plans of Afghanistan and Cuba;
the refrigerant management plans (RMP) in Burkina Faso, Brunei Darussalam, Haiti
and Myanmar: methyl bromide phase-out projects in Bolivia, Cuba, Kyrgyzstan, Sri
Lanka; the technical assistance programme for Africa (UNDP); and the China halon
sector plan and the China sector plan for TCA production phase-out.
The
Executive Committee took note of the reports submitted and made a number of
requests for individual governments, in collaboration with the relevant
implementing agencies, to take action on issues raised. In the case of the TCA
production phase-out project in China, the Committee commended the Government
and the World Bank on achieving the production reduction targets as specified in
the agreement.
Project
approvals (decisions 51/17 – 51/33)
The
Secretariat had received funding requests with a total value of some US $61.8
million. 49 projects and activities for 32 developing countries were approved at
a cost of US $50.7 million plus US $3.9 million in support costs for
implementing agencies. These projects and activities would fund the phase-out of
over 3,719 ODP tonnes of ODS consumption and 16,695 ODP tonnes of production.
Projects approved by the Executive Committee included US $24 million for China
to dismantle the remaining CFC production plants thus ending production of CFCs
more than two years ahead of the 2010 CFC phase-out deadlines, extensions to
institutional strengthening projects in nine countries, and several tranches for
multi-year agreements. A total of US $2 million in funding was agreed in
principle for terminal phase-out plans in Bolivia, the Seychelles, Paraguay and
Zimbabwe.
Metered-dose Inhalers (decision 51/34)
At its
51st Meeting, the Executive Committee considered the specific circumstances of
some Article 5 Parties with plants manufacturing CFC metered-dose inhalers (MDIs),
but which had committed to phasing-out all the remaining CFC consumption in
their country without further requests for funding. The discussion also covered
strategies for the transition to non CFC MDIs in Article 5 countries without
CFC-MDI production facilities.
In regard
to providing assistance for CFC phase-out for Parties with locally owned MDI
manufacturing facilities, the Committee considered the following main issues:
the cut off date for the establishment of CFC-MDI production lines, the base
year for establishing the consumption of CFCs for this application, funding
eligibility, the time scale for payment of operating costs and the availability
of pharmaceutical-grade CFCs. During the discussion, several Members recognized
the potential difficulties faced by several Parties in phasing out their
consumption of CFCs for the production of MDIs. However, it was also noted that
several of the Article 5 countries in question had undertaken to phase-out all
of their CFC consumption under approved phase-out plans, and thus assistance for
such countries should be examined on a case-by-case basis and be subject to
several conditions. On the issue of the cut-off date for the establishment of
CFC-MDI production lines, some members pointed out that developing countries had
not had access to CFC phase out technology for the MDI sector before 1995. On
the issue of transition strategies, it was tentatively suggested that the
conditions for funding transition strategies could be extended to all eligible
non CFC MDI producing Article 5 Parties on the condition that they provided
basic data documenting and demonstrating the need for such a strategy, as
indicated in decision 45/54 on preparation and submission of TPMPs.
The
Executive Committee decided to advise Article 5 countries with plants
manufacturing CFC MDIs that the planning for any essential use exemption
nominations might begin in 2007 for submission to the Parties to the Montreal
Protocol for their consideration in 2008. The Committee decided that it would
need to consider further the availability of pharmaceutical grade CFCs after
2010 in light of TEAP reports to the 27th Meeting of the OEWG and the 19th MOP
on campaign production of CFCs for MDIs in Article 5 and non Article 5 Parties.
Terms of
reference for the study on the treatment of unwanted ODS
At the
50th Meeting the Executive Committee requested the Secretariat to develop terms
of reference, to identify a contractor, and to commission the study by the end
of March 2007 in order to complete it by February 2008. The study would look at
the management of unwanted ODS in non-Article 5 countries and how this might be
applicable in Article 5 countries. The Committee noted the progress made in
contracting a consultant to carry out the study and the detailed terms of
reference. The outline of the study and a work plan would be available before
the 52nd Meeting of the Executive Committee, and would form the basis of the
report to the 19th MOP to the Montreal Protocol.
Report of
the Executive Committee to the Open-ended Working Group on the progress made in
reducing emissions of controlled substances from process agent uses (decision
51/35)
The
Executive Committee examined an update to the report presented at their 45th
Meeting on process agent uses and their related emission levels in Article 5
countries. This report had been prepared in response to decision XVII/6 of the
17th MOP which requested the TEAP and the Executive Committee to report to the
OEWG at its 27th Meeting in 2007. The update presented the projects and
activities which had been funded by the Multilateral Fund since the 45th Meeting
and the progress, where known, that had been achieved by the projects funded,
in reducing emissions from the applications controlled by the Montreal
Protocol. A final report, including additional information regarding
differences between country programme data and Article 7 data and relevant
information from the Chemical Technical Options Committee, would be submitted to
the 27th OEWG in June 2007.
Consideration of the issue of CTC use as feedstock and process agents, and the
co-production of CTC in Article 5 countries (decision 51/36)
At its
48th Meeting, the Executive Committee decided to consider the issue of CTC use
as feedstock and process agents and the co-production of CTC in Article 5
countries at its 51st Meeting (decision 48/27). Consideration of this issue
was deferred until the 52nd Meeting when the study of the TEAP on global CTC
emissions would be available.
Assessment
of the administrative costs required for the 2009-2011 triennium (decision
51/38)
The
Executive Committee adopted draft terms of reference for a comprehensive
independent assessment of the administrative costs required for the 2009-2011
triennium. Core unit costs and agency fees constitute administrative costs and
are intended to provide implementing agencies with funds for administrative
tasks, personnel, and other general administrative services associated with
projects implementation. The Fund Secretariat would present the costs, based
on bids received from qualified consultants, to the Executive Committee at its
52nd Meeting.
Secretariat budget (decision 51/39)
At the
50th Meeting the Executive Committee had approved the budget of the Fund
Secretariat, including the amount of US $500,000 for the 2007 treasury fee,
while withholding US $200,000 of that total sum until the issue of the P5
treasury position was resolved (decision 50/45). As a result of successful
discussions with UNEP, the amount of US $200,000 was released. On the issue of
the P5 post to deliver treasury services to the Multilateral Fund, the Committee
agreed to the upgrade of the post of the Administrative and Fund Management
Officer to P5. It also revised the Secretariat’s budget to reflect both the
upgrade of the post from P4 to P5 and the cost estimate of the study on
administrative costs.
52nd and
53rd Meetings of the Executive Committee
It was
confirmed that the Executive Committee’s 52nd and 53rd Meetings would be held in
Montreal from 23 to 27 July 2007 and from 26 to 30 November 2007, respectively.
Report of
the 51st Meeting
A complete
record of all decisions made at the 51st Meeting, including those covered in
this document, can be found in the ‘Report of the Fifty-first Meeting of the
Executive Committee of the Multilateral Fund for the Implementation of the
Montreal Protocol’ (UNEP/OzL.Pro/ExCom/51/46) on the Multilateral Fund’s website
(www.multilateralfund.org). The report is available in Arabic, Chinese, English,
French, and Spanish.