The Executive Committee decided:
(a) To take note of the 2003 consolidated project completion report, as contained in document UNEP/OzL.Pro/ExCom/41/8 and Add.1, including the schedule for submission of project completion reports due;
(b) To request the World Bank, in cooperation with the Fund Secretariat, to establish full consistency of data reported in the project completion reports, in the inventory and in the annual progress reports by the end of January 2004;
(c) Also to request UNDP and the World Bank to provide the information still missing in a number of project completion reports by the end of January 2004;
(d) To urge implementing agencies to continue to improve their descriptive assessments of completed projects in project completion reports, while at the same time ensuring that each assessment contained useful information specific to the project that was the subject of the report; and
(e) To request the Senior Monitoring and Evaluation Officer to provide the Executive Committee with information compiled on the lessons learned from project completion reports.
(Decision 41/6)