Agenda: Business planning

Agenda item

5(a)(ii) 

Main title

Business planning 

Sub-title 1

Strategic business planning (Decisions 41/80 (e) and 41/81) 

Sub-title 2

Three-year phase-out plan 2004-2006 

Agenda Date

3/29/2004 3:30 PM 

Background

Document UNEP/OzL.Pro/ExCom/42/5:  contains, the model rolling three year phase-out plan for the Multilateral Fund for the years 2004-2006.  The paper includes an analysis of the amounts of ODS that needs to be approved for funding to enable all Article 5 countries to achieve the 2005 and 2007 Montreal Protocol phase out targets plus partial phase-out of the remaining ODS consumption to achieve the 2010 phase-out targets.  The paper indicates the ODSs to be phased out in Article 5 countries during the triennium in approved multi-year sectoral and national phase-out plans, and individual and umbrella projects, and the number of RMPs and TPMPs under current implementation in low-volume consuming countries. 

Document1

UNEP/OzL.Pro/ExCom/42/5 

Document2

 

Document 3

 

Issues

• Whether the paper provides a satisfactory basis for planning the phase-out to be achieved through Multilateral Fund projects and activities, and for business planning for the corresponding triennium. 
• The very high level of phase-out that needs to be achieved from already approved projects and the need to ensure successful and timely implementation

Actions

The Committee may wish to:

(a) Note that the draft model three-year phase-out plan 2004-2006 presented in this document was used as the basis for the preparation of the 2004-2006 business plans of the implementing agencies;
(b) Consider adopting the model three-year phase-out plan 2004-2006 as a flexible guide for resource planning for the corresponding triennium;
(c) Urge Article 5 countries with approved but not implemented projects and the cooperating implementing and bilateral agencies to accelerate the pace of implementation during the 2004-2006 triennium; and
(d) Request the Secretariat to present an updated model three-year rolling phase-out plan for the years 2005-2007 to the first meeting in 2005 to provide guidance as relevant for the preparation of the 2005-2007 business plan of the Multilateral Fund.

Related decision (1)

Decision 41/80 

Related Decison (2)

Decision 41/81 

Related document1

UNEP/OzL.Pro/ExCom/42/5 

Related document2

 

Related document 3

 

Sort number

5.12 
Attachments
Created at 3/4/2004 11:14 AM  by Julia Dearing 
Last modified at 3/29/2004 1:52 PM  by Julia Dearing