Business planning
Agenda
: Business planning
Agenda item
5(a)(ii)
Main title
Business planning
Sub-title 1
Strategic business planning (Decisions 41/80 (e) and 41/81)
Sub-title 2
Three-year phase-out plan 2004-2006
Agenda Date
3/29/2004 3:30 PM
Background
Document UNEP/OzL.Pro/ExCom/42/5: contains, the model rolling three year phase-out plan for the Multilateral Fund for the years 2004-2006. The paper
includes an analysis of the amounts of ODS that needs to be approved for funding to enable all Article 5 countries to achieve the 2005 and 2007 Montreal Protocol phase out targets plus partial phase-out of the remaining ODS consumption to achieve the 2010 phase-out targets. The paper indicates the ODSs to be phased out in Article 5 countries during the triennium in approved multi-year sectoral and national phase-out plans, and individual and umbrella projects, and the number of RMPs and TPMPs under current implementation in low-volume consuming countries.
Document1
UNEP/OzL.Pro/ExCom/42/5
Document2
Document 3
Issues
• Whether the paper provides a satisfactory basis for planning the phase-out to be achieved through Multilateral Fund projects and activities, and for business planning for the corresponding triennium.
• The very high level of phase-out that needs to be achieved from already approved projects and the need to ensure successful and timely implementation
Actions
The Committee may wish to:
(a) Note that the draft model three-year phase-out plan 2004-2006 presented in this document was used as the basis for the preparation of the 2004-2006 business plans of the implementing agencies;
(b) Consider adopting the model three-year phase-out plan 2004-2006 as a flexible guide for resource planning for the corresponding triennium;
(c) Urge Article 5 countries with approved but not implemented projects and the cooperating implementing and bilateral agencies to accelerate the pace of implementation during the 2004-2006 triennium; and
(d) Request the Secretariat to present an updated model three-year rolling phase-out plan for the years 2005-2007 to the first meeting in 2005 to provide guidance as relevant for the preparation of the 2005-2007 business plan of the Multilateral Fund.
Related decision (1)
Decision 41/80
Related Decison (2)
Decision 41/81
Related document1
UNEP/OzL.Pro/ExCom/42/5
Related document2
Related document 3
Sort number
5.12
Attachments
Created at 3/4/2004 11:14 AM by Julia Dearing
Last modified at 3/29/2004 1:52 PM by Julia Dearing
Use this page to add attachments to an item.
Name